Project History

During our initial planning stage, we decided on the following guidelines for choosing our school's location.

1: Within reasonable travel distance from Beijing
2: Mandarin chinese speaking community (so that in future we can facilitate language teachers)
3: An area with demonstrable need
4: Acceptable plans for school
5: Agreement for future cooperation and maintenance.

With these parameters in mind we have decided to build the CNYTrust School in Hebei

1: Travel to school from Beijing by car requires around eight hours
2: Mandarin chinese speaking community but with a variety of minority ethnicities represented
3: Education facilities currently exist but are limited to scattered non purpose built mud houses and a larger purpose built school constructed in the early 1970's out of mud and clay bricks. This facility has recently been classed level "D" by a visiting government education inspector (A being safe and E being non usable) in terms of building stability.
4: Current plans have the school building being a two storey facility with a capacity to accomodate for 300 students. The building would serve a large catchment area, replacing most existing facilities. Local authorities have pledged a total sum of RMB400,000 contingent on a further RMB200,000 being raised by an outside sponsor. CNYTrust believes that this represents a project with both acceptable plans and much promise for future further development.
5: CNYTrust representatives have visited the school site, negotiated terms for future cooperation and maintenance of the school and have found its future partners for the school to be highly capable.

Project reports

In our commitment to transparency we publish detailed reports on the progress of our school project, on what events were used to raise funds and how these funds were used. Please find our current reports below:

 